Skip to main content

Babb Creek Antrim Mine Treatment Plant

Babb Creek Antrim Mine Treatment Plant

Project Details
Original Construction Year 1996
Most Recent Rebuild Year
Total Cost $1,021,258.00
Total Capital Cost $2,000,000.00
Latitude / Longitude Method Unknown
Latitude 41.629444
Longitude -77.286389
Elevation 0
Project Babb Creek Antrim Mine Treatment Plant
Project Type Active Treatment System
Project Status
AMD Source Underground
Stream Wilson Creek
Watershed
River Basin Susquehanna
Quad Antrim
City/Township Duncan
County Tioga
State PA

Description:

Water Quality Data Summary

Treatment Technologies
Treatment Technology Quantity Status
Chemical Treatment Plant 1 N/A
Location Links
Map
GPS Directions
Project Contacts
Contact Person:
Contact Organization:
Project Designer:
Project Designer Organization:
Project Responsible Organization: Babb Creek Watershed Association
Organizations
no data available
External System IDs
Title System
D1-453 Datashed 1.0
PA-94 OSM
Project Performance